If you need to edit, or release, the retainage for line items on an invoice, you can do so by following the steps below.
To Edit Retainage:
- From the My Projects page, select the project you wish to work in.
- Click Cost Tracking (may also be called "Contract Mgmt") from the left-hand menu.
- Click Invoices / Pay Apps thread (may also be called "Invoices").
- Select the open Invoice item you wish to edit.
Helpful Hint: The retainage can only be edited for an invoice that has not yet been approved.
- On the Items tab, click the Edit icon.
Helpful Hint: The screen will refresh and the % WC Retainage and % MS Retainage fields will become editable textboxes.
- Enter the changes you want in these textboxes.
Helpful Hints:
- Change the retainage value to '0.00' to release all of the retainage for that line item.
- % WC Retainage refers to the retainage percent for "Work Completed".
% MS Retainage refers to the retainage percent for "Materials Stored". - Retainage is calculated according to AIA principles, meaning it builds from previous payments. If you wish to pay balances at different retainage amounts, it is a best practice to separate the amounts into different line items.
- Hit Save to keep the changes.